- By David Wilma
- Posted 9/16/2004
- HistoryLink.org Essay 5733
Des Moines Mayor Bob Sheckler stated, “Our efforts over the past 10 years have resulted in enormous gains for the communities that surround the airport and the people who are affected by its operations. The Port, the FAA and the state of Washington have stepped up to provide $150 million to our schools to improve our children’s learning environment, thousands of homes have been insulated to reduce the effects of jet noise and the most stringent permits in the history of our state have been issued that will protect our streams and environmentally sensitive areas from the impacts of the third runway” (Tribune).
The third runway was needed because the existing two runways were too close together and only one could be used in bad weather. The third runway was completed in 2008 at a cost of more than $1 billion.
Sources:
John Gillie, “Foes of Third Runway Fight Give Up 10-Year Fight,” The Tribune (Tacoma), August 20, 2004, p. A-1.