TagLockridge Grindal Nauen(75)
-
2021-09-02
City of Des Moines Agenda Item: Consultant Contract Amendment for Sea-Tac Airport Sustainable Airport Master Plan Environmental Review and Analysis
The City of Des Moines, WA considered an amendment to a consultant contract supporting a coordinated environmental review of the Port of Seattle's Sea-Tac Airport Sustainable Airport Master Plan (SAMP), a 20-year airport growth plan. The amendment adds $100,000 to the original $175,000 contract, extends its term to 2023, and shifts contract administration from SeaTac to Des Moines, with costs shared among Des Moines, Burien, Normandy Park, and SeaTac based on population. The consultant, now operating as Primacy Strategy Group LLC, assists the four cities in reviewing and responding to environmental documents and impacts related to the SAMP process under NEPA and SEPA. -
2020-03-23
Third Amendment to Consultant Contract between the City of Sea-Tac, the City of Burien, and Lockridge Grindal Nauen PLLP
This Third Amendment to a consultant contract between the City of SeaTac, the City of Burien, and Lockridge Grindal Nauen PLLP extends the contract term to December 31, 2021, while suspending all consultant services starting January 1, 2020, until the SeaTac Airport Master Plan (SAMP) environmental review documents are released for public comment. The suspension was put in place due to delays in the SEPA/NEPA environmental review process, which was not expected to conclude until late 2020 or early 2021. The amendment also acknowledges that Aviation Compatibility Consulting, LLC and ABCx2, LLC have combined, with services to be performed jointly by Lockridge Grindal Nauen P.L.L.P. and ABCx2, LLC. -
2020-03-23
Third Amendment to Consultant Contract between the City of Sea-Tac, the City of Burien, and Lockridge Grindal Nauen PLLP
This Third Amendment to a consultant contract between the City of SeaTac, the City of Burien, and Lockridge Grindal Nauen PLLP extends the contract term to December 31, 2021, while suspending all consultant services starting January 1, 2020, until the SeaTac Airport Master Plan (SAMP) environmental review documents are released for public comment. The suspension was put in place due to delays in the SEPA/NEPA environmental review process, which was not expected to conclude until late 2020 or early 2021. The amendment also acknowledges that Aviation Compatibility Consulting, LLC and ABCx2, LLC have combined, with services to be performed jointly by Lockridge Grindal Nauen P.L.L.P. and ABCx2, LLC. -
2020-01-15
Lockridge Grindal Nauen Invoice #8: City of Burien SAMP Legal Services, August 2019
This document details billing records from Lockridge Grindal Nauen P.L.L.P., a law firm hired jointly by the cities of Burien, Des Moines, Normandy Park, and SeaTac to conduct an environmental review of the Sea-Tac Airport Sustainable Airport Master Plan (SAMP). Under an Interlocal Agreement signed March 6, 2018, the cities shared a total contract of $175,000, with costs split proportionally by population. Invoice #8, dated January 15, 2020, covers legal work performed in August 2019, bringing the total billed to date to approximately $88,879 out of the $175,000 contract. -
2020-01-15
City of Burien Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
This document details billing records for the City of Burien, Washington, related to the Sea-Tac Airport Sustainable Airport Master Plan (SAMP) environmental review. Four cities — Burien, Des Moines, Normandy Park, and SeaTac — jointly hired law firm Lockridge Grindal Nauen PLLP under a $175,000 contract, with each city's share calculated at approximately $1.50 per capita. Through eight invoices spanning 2018 to early 2020, a total of $88,879.33 had been billed, leaving a remaining balance of $86,120.67. -
2020-01-15
Lockridge Grindal Nauen Invoice #8: City of Burien SAMP Legal Services, August 2019
This document details billing records from Lockridge Grindal Nauen P.L.L.P., a law firm hired jointly by the cities of Burien, Des Moines, Normandy Park, and SeaTac to conduct an environmental review of the Sea-Tac Airport Sustainable Airport Master Plan (SAMP). Under an Interlocal Agreement signed March 6, 2018, the cities shared a total contract of $175,000, with costs split proportionally by population. Invoice #8, dated January 15, 2020, covers legal work performed in August 2019, bringing the total billed to date to approximately $88,879 out of the $175,000 contract. -
2020-01-15
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington maintained billing records for a joint legal consulting contract with Lockridge Grindal Nauen PLLP to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP). Four cities — Burien, Des Moines, Normandy Park, and SeaTac — shared the $175,000 contract cost based on their respective populations, at approximately $1.50 per capita. By January 2020, a total of $88,879.33 had been billed across eight invoices, leaving a remaining balance of $86,120.67. -
2020-01-15
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington maintained billing records for a joint legal consulting contract with Lockridge Grindal Nauen PLLP to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP). Four cities — Burien, Des Moines, Normandy Park, and SeaTac — shared the $175,000 contract cost based on their respective populations, at approximately $1.50 per capita. By January 2020, a total of $88,879.33 had been billed across eight invoices, leaving a remaining balance of $86,120.67. -
2020-01-15
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington managed billing for a joint legal consulting contract with Lockridge Grindal Nauen PLLP to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP) on behalf of four cities: Burien, Des Moines, Normandy Park, and SeaTac. The $175,000 contract was funded proportionally based on each city's population at approximately $1.50 per capita, with costs shared across eight invoices between September 2018 and January 2020. As of the most recent billing, approximately $88,879 of the total contract had been billed, leaving roughly $86,121 remaining. -
2020-01-15
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington managed billing for a joint legal consulting contract with Lockridge Grindal Nauen PLLP to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP) on behalf of four cities: Burien, Des Moines, Normandy Park, and SeaTac. The $175,000 contract was funded proportionally based on each city's population at approximately $1.50 per capita, with costs shared across eight invoices between September 2018 and January 2020. As of the most recent billing, approximately $88,879 of the total contract had been billed, leaving roughly $86,121 remaining.