TagSea-Tac Airport(1835)
-
2002-01-01
Sea-Tac Airport Third Runway Embankment Construction Earthwork (2002)
Aerial photograph showing large-scale earthwork and grading operations during construction of Seattle-Tacoma International Airport's third runway (Runway 16C/34C). The image shows the runway surface and surrounding excavated terrain, with the existing airport facilities and control tower visible in the background. -
2002-01-01
FAR Part 150 Study Table: Airport Noise Restrictions and FAR Part 161 Compliance Requirements
A table from the Sea-Tac International Airport FAR Part 150 Study listing airport actions (such as limiting aircraft by noise level, time of day, type, and runway use) and indicating whether each action definitively requires FAR Part 161 compliance or may potentially trigger it. Actions including limiting training activities, restricting runway use, and lease provisions indirectly affecting noise are marked with '?' under 'Requires Part 161' but 'Yes' under 'May Trigger Part 161.' -
2001-12-28
EXH AR027061: Ecology Acknowledgment of Waste Discharge Permit Application WA-002465-1 and Port Of Seattle NPDES Permit Renewal Submission for Sea-Tac Airport
AR027061. Two letters dated December 2001 regarding NPDES Permit WA-002465-1 for Seattle-Tacoma International Airport. First: Washington Department of Ecology (Tricia Miller, Permit Coordinator, Northwest Regional Office) acknowledges receipt of a waste discharge permit application from Michael Feldman, Director of Aviation Facilities, Port Of Seattle, received December 21, 2001; contact Ed Abbasi at (425) 649-7227. Second -
2001-12-20
EXH AR031428: U.S. Fish & Wildlife Service Comments on Monitoring Plan for Embankment Fill Seepage, Master Plan Update ESA Consultation (1-3-00-F-1420)
Letter dated December 20, 2001 from Ken S. Berg, Manager, Western Washington Fish and Wildlife Office (U.S. Fish & Wildlife Service) to James M. Lynch, Stoel Rives LLP, providing 20 numbered comments on the Monitoring Plan for Embankment Fill Seepage submitted August 10, 2001 under Endangered Species Act consultation 1-3-00-F-1420 (Sea-Tac Airport Master Plan Update). -
2001-12-20
EXH AR026603: Letter USFWS to James M. Lynch — Monitoring Plan Embankment Fill Seepage, Master Plan Update ESA Consultation (1-3-00-F-1420)
This December 2001 letter from the U.S. Fish and Wildlife Service's Western Washington office provides detailed comments on a Monitoring Plan for Embankment Fill Seepage related to a Sea-Tac Airport Master Plan Update, reviewed under the Endangered Species Act. The agency requested key revisions, including monitoring both seepage quality and quantity, beginning monitoring when seepage first occurs rather than after embankment completion, and ensuring groundwater wells are considered as a monitoring pathway. The letter also clarified that any exceedances of water quality criteria must be reported promptly, and that the Federal Aviation Administration—not the Port—would be responsible for reinitiating formal consultation. -
2001-12-20
EXH AR053223: Effect of Shear Modulus on Deformations and Reinforcing Stresses of MSE Walls — Third Runway Project
Memorandum dated December 20, 2001 from Michael Bailey, P.E. and Reda A. Mikhail, P.E. of Hart Crowser, Inc. to Jim Thomson, P.E. of HNTB Corporation regarding AR053223, project 4798-40. Analyzes sensitivity of MSE (Mechanically Stabilized Earth) wall design to variations in soil shear modulus under dynamic/seismic loading for the Third Runway Project at Sea-Tac Airport, -
2001-12-12
EXH AR053195: Hydrologic Conditions and Wetland Hydrology, Borrow Area 1 — Hart Crowser Memorandum
Memorandum dated December 12, 2001 from Michael Kenrick and Reese Hastings of Hart Crowser Inc. to Jim Thomson of HNTB, project number 4978-62, analyzing pre-construction and post-construction hydrologic conditions at Borrow Area 1 associated with the Port of Seattle Master Plan Update for Sea-Tac International Airport (STIA). Covers surface water and groundwater impacts, wetland hydrology, -
2001-12-01
EXH 297: Low Streamflow Analysis Summer Low Flow Impact Offset Facility Proposal STIA Master Plan Update
This December 2001 report, prepared by Parametrix, Inc. and several partner firms for the Port of Seattle, analyzes low streamflow conditions and proposes a Summer Low Flow Impact Offset Facility as part of the Seattle-Tacoma International Airport Master Plan Update Improvements. The study examines how planned airport expansion may affect seasonal low-flow water resources in the surrounding area and outlines mitigation measures to offset those impacts. The report is organized across multiple volumes, with Volume 1 containing the main text and Appendices B through J. -
2001-12-01
EXH AR052659: Low Streamflow Analysis and Summer Low Flow Impact Offset Facility Proposal — Seattle-Tacoma International Airport Master Plan Update Improvements
Parametrix, Inc. report prepared for Port of Seattle, Seattle-Tacoma International Airport Master Plan Update Improvements, December 2001. AR 052659/052660/052661. Volume 1 includes main text and Appendices B through J. Sub-consultants include Aqua Terra Consultants, Earth Tech Inc., Foster Wheeler Environmental Corporation, HNTB, and Pacific Groundwater Group. Addresses low streamflow analysis and summer low flow impact -
2001-12-01
EXH AR030065: Wetland Functional Assessment and Impact Analysis — Master Plan Update Improvements, Sea-Tac Airport
Wetland Functional Assessment and Impact Analysis prepared by Parametrix, Inc. for Port Of Seattle, December 2001, project number 556-2912-001 (03). Assesses wetland functions and impacts associated with Seattle-Tacoma International Airport Master Plan Update Improvements including the new Third Runway, Runway Safety Areas (RSAs), relocation of South 154th Street, Borrow Area 1 excavation, South Aviation Support