Sustainable Airport Master Plan (SAMP): City of Des Moines Council briefing
This May 2015 briefing presented the Port of Seattle's Sustainable Airport Master Plan (SAMP) for Seattle-Tacoma International Airport to the City of Des Moines Council. The plan addresses rapid passenger and operations growth within a constrained airport footprint, outlining the need for strategic land use planning, potential expansion onto additional Port-owned properties, and relocation of existing facilities to maintain airfield capacity and add terminal capacity. Key topics covered include economic impact, sustainability, activity forecasts, development constraints, and public outreach. -
2015-03-01
Technical Memorandum No. 2: Inventory of Existing Conditions — Seattle-Tacoma International Airport
This 2015 technical memorandum prepared by Leigh Fisher for the Port of Seattle provides a comprehensive inventory of existing conditions at Seattle-Tacoma International Airport as part of the Sustainable Airport Master Plan. It covers a wide range of airport infrastructure and operations, including airfield runways and taxiways, passenger terminal facilities, ground transportation, air cargo, general aviation, and airline and airport support systems. The document serves as a baseline assessment of the airport's physical and operational state to inform future planning decisions. -
2015-03-01
Technical Memorandum No. 2: Inventory of Existing Conditions — Seattle-Tacoma International Airport
Technical Memorandum No. 2 (Final) prepared by Leigh Fisher in association with Architecture Building Culture for the Port of Seattle, dated March 2015, as part of the Sustainable Airport Master Plan (SAMP) for Seattle-Tacoma International Airport. Documents existing conditions across all major airport systems including: airfield (runways, taxiways, non-conforming conditions, weather occurrence, runway use patterns, -
2014-12-31
Port Of Seattle Aviation Properties Overview Map — December 2014
This is an official Port of Seattle Aviation Properties Overview map (Page 02), published December 31, 2014, depicting zone boundaries around Seattle-Tacoma International Airport (Sea-Tac). The map identifies six named zones — Airfield (p.92), Terminal (p.83), Commercial (p.34), North of Airfield (p.3), South of Airfield (p.103), and South of 200th (p.120) — plus an Auburn inset (p.126), with a zone key distinguishing Port of Seattle property, lease boundaries, zone matchline boundaries, and land available for development. -
2014-12-31
FAA/TRACON lease information
This document describes a Port of Seattle ground lease (Lease #000273) with the FAA/TRACON facility located on the west side of the airfield in SeaTac, Washington. The lease covers approximately 832,011 square feet, was set to expire on September 30, 2022, and includes two renewal options extending until 2062, each for a period of 20 years. The facility serves an aeronautical terminal radar function and is subject to bond and Airport Improvement Project (AIP) funding restrictions that require coordination with Airport Finance & Budget before any changes in property use. -
2014-12-31
Comprehensive annual financial report: Port Of Seattle
This is the Port of Seattle's Comprehensive Annual Financial Report covering financial data as of December 31, 2014 and 2013, and for the years ended December 31, 2014, 2013, and 2012. Prepared by the Port's Accounting and Financial Reporting Department, the report provides a detailed account of the Port's financial position and activities, which include operations at Seattle-Tacoma International Airport and the regional seaport. It serves as an official public record of the Port of Seattle's financial performance during those fiscal years. -
2014-12-31
Aircraft Service International, Inc. lease information
Aircraft Service International, Inc. leases 29,569 square feet at 18291 Starling Road in SeaTac, WA (Lease #000765), located at the south end of the Sea-Tac Airfield inside the security fence, where it operates as a Fixed Base Operator (FBO) providing general aviation terminal services. The lease expired April 30, 2021, with no renewal options, transitioning to a month-to-month holdover arrangement, and includes a termination clause requiring 180 days notice for capital projects and a 30-day relocation notice. Parties seeking to modify the property's use must consult Corporate Finance & Budget regarding bond restrictions and Airport Finance & Budget regarding Airport Improvement Project (AIP) funding conditions. -
2014-12-09
Grant closeout letter: AIP grant number 3-53-0062-131-2013
The Federal Aviation Administration (FAA) issued a grant to the Port of Seattle to fund noise mitigation work at Olympic Elementary School near Seattle-Tacoma International Airport, with a maximum federal contribution of $3.9 million covering 80% of allowable project costs. The grant (AIP Grant Number 3-53-0062-131-2013) was formally closed out on December 9, 2014, with a final paid amount of $3,879,406 after all work was confirmed satisfactorily completed and costs verified as reasonable and eligible. The Port of Seattle is required to retain all supporting project documentation for a minimum of three years from the final reimbursement request, in accordance with Federal Regulation 49 CFR Part 18.42. -
2014-12-02
SEPA Environmental checklist: Seattle-Tacoma International Airport (STIA) North Satellite (NSAT) Terminal Expansion
This SEPA environmental checklist prepared by the Port of Seattle covers the proposed renovation and expansion of the North Satellite Terminal at Seattle-Tacoma International Airport. The project would expand the terminal footprint from 91,500 to 154,500 square feet, adding eight new airplane gates for a total of twenty contact gates. Construction was planned in two -
2014-12-02
Environmental checklist: Seattle-Tacoma International Airport (STIA) North Satellite (NSAT) Terminal Expansion
This SEPA environmental checklist prepared by the Port of Seattle covers the proposed renovation and expansion of the North Satellite Terminal at Seattle-Tacoma International Airport. The project would expand the terminal footprint from 91,500 to 154,500 square feet, adding eight new airplane gates for a total of twenty contact gates. Construction was planned in two