TagPollution Control Hearings Board(1532)
-
2001-02-08
Exhibit 2060: Ecology Response to PDA Requests on Dam Safety and MSE Wall Review, Plus Memorandum on Retaining Wall Alternatives for Miller Creek
Email dated February 8, 2001 from Ann Kenny (Ecology Senior Environmental Specialist) to Andrea Grad, Peter Eglick, and Kevin Stock responding to PDA requests regarding Chapter 173-175 WAC Dam Safety review of Port Of Seattle Third Runway stormwater facilities. Covers ISW Lagoon #3, 25.5 acre-foot pond (SDW1A), 37.91 acre-foot pond (SDW1B), MSE wall Dam Safety -
2001-02-08
EXH AR049869: Hart Crowser Letter — Comments on 404/401 Permit Applications for Port Of Seattle Third Runway MSE Retaining Walls
Letter dated February 8, 2001 from Hart Crowser Principal Geotechnical Engineer to U.S. Army Corps of Engineers (Jonathan Freedman) and Washington State Department of Ecology (Ann Kenny), documenting comments made at the January 26, 2001 public hearing on 404/401 permit applications J-4978-30-06. Comments focus on the design and independent technical review of mechanically stabilized earth -
2001-02-08
EXH AR023692: Ecology Audit Request, Grant, Agreed Order #97T-N122, STIA
In February 2001, a Washington State Department of Ecology site manager requested an audit of a Port of Seattle grant (Grant No. G0000052) tied to Agreed Order #97T-N122, citing concerns about potential duplicate funding where costs could be covered by both the grant and cost recovery from other parties. The grant, worth up to $861,000 (split 50/50 between state and local funds), was issued to support a Phase 1 groundwater study at Seattle-Tacoma International Airport (Sea-Tac), investigating contamination from jet fuel and petroleum products released from underground storage tanks and fuel distribution systems. The study aimed to model groundwater flow and assess risks to nearby public drinking water wells and surface water bodies. -
2001-02-07
Exhibit 2059: Email and Memorandum on Retaining Wall/Slope Alternatives to Reduce Impacts to Miller Creek, Third Runway at Sea-Tac Airport
Exhibit 2059 (AR 031711–031713, ECY00010776–10778). Email from Gus Ordonez to Ann Kenny dated February 7, 2001, transmitting a memorandum from Jerald LaVassar, M.S., P.E. to Tom Luster reviewing the report ‘Evaluation of Retaining Wall/Slope Alternatives to Reduce Impacts to Miller Creek, Embankment Station 174+00 to 186+00’ for the Third Runway project at Sea-Tac International Airport. -
2001-02-01
EXH AR026134: Guidelines Preparing Quality Assurance Project Plans Environmental Studies
This Washington State Department of Ecology publication, authored by Stewart M. Lombard and Cliff J. Kirchmer and released in February 2001, provides guidelines for preparing Quality Assurance Project Plans (QAPPs) for environmental studies. It outlines standards and procedures to ensure that data collected during environmental investigations meets defined quality and reliability requirements. -
2001-01-28
EXH 386: Field Notes – Ace Airport View Site Visit, Des Moines Creek Outfall & Wetland Obs, Jan 28 2001
Field notes dated 1/28/01 document an inspection of Ace Airport View, recording observations at a stormwater detention station (DM1 - Monitoring Station) near Des Moines Creek. The inspector noted a turbid outfall at SDS-1 in the southwest, associated wetlands, steep sides, and the presence of an oil boom, with water samples collected at 11:45 AM by Dr. Strand. Additional notes reference a southwest pond draining adjacent to the creek, clogging of material at outfall infrastructure, and embankment flows requiring attention to discharge locations. -
2001-01-28
EXH AR053366: Handwritten Field Notes — Ace Airport View Site Visit, January 28, 2001
Handwritten field notebook entries dated 1/28/01 documenting a site visit to Ace Airport View (DM1 – Monitoring Station) near Des Moines, referencing Des Moines Creek, SDS 1 outfall into SW associated wetlands, steep side terrain, oil boom present in unit 2, turbid water, black stones, water from outfall significantly turbid, Dr. Strand took samples at -
2001-01-25
EXH AR023689: Notes 3RW Public Meetings & Hearings Jan 26-27 2001
These are prepared talking points for Washington State Department of Ecology officials attending public meetings on January 26-27, 2001, regarding the proposed Third Runway (3RW) at Seattle-Tacoma International Airport. The notes address 17 anticipated public questions covering topics such as Ecology's 401 Water Quality Certification review process, the use of Port-funded consultants, SEPA compliance, wetlands impacts, and whether the project was receiving special political consideration. Officials emphasized that no approval would be granted until the project demonstrated full compliance with all applicable environmental laws and regulations. -
2001-01-25
EXH AR049834: Hart Crowser Memorandum — Additional Information on the Seismic Design for Sea-Tac International Airport Third Runway
Memorandum dated January 25, 2001 from Douglas Lindquist (EIT) and Michael Bailey (P.E.) of Hart Crowser, Inc. to the Embankment Technical Review Board (Attn: Pete Douglass), project J-4978-30, CC to Jim Thomson (P.E., HNTB). Provides additional information on seismic analyses for the Third Runway at Seattle-Tacoma International Airport (STIA) in SeaTac, Washington. Covers probabilistic seismic -
2001-01-25
EXH AR049866: Letter from Peter M. Douglass, Technical Review Board Facilitator, Regarding Third Runway Embankment Fill and MSE Wall Design Review
Letter dated January 25, 2001 from Peter M. Douglass, P.E. (Technical Review Board Facilitator) to U.S. Army Corps of Engineers (Jonathan Freedman, Project Manager) and Washington State Department of Ecology (Ann Kenny, Environmental Specialist) summarizing findings of an independent expert panel convened by Port Of Seattle to review embankment fill and mechanically stabilized earth (MSE)