TagPollution Control Hearings Board(1532)
-
2002-01-29
EXH AR004685: ACC’s Reply on Motion for Summary Judgment Regarding the Absence of a Water Right for Third Runway § 401 Certification
Airport Communities Coalition (ACC) reply brief filed January 29, 2002 in PCHB No. 01-160 before the Pollution Control Hearings Board (PCHB), State of Washington, supporting ACC’s Motion for Summary Judgment on the absence of a water right for the Third Runway Section 401 Water Quality Certification (#1996-4-02325). ACC argues the Port Of Seattle’s Low Flow -
2002-01-28
EXH I: Standing Water on Fill Embankment S 160th St 28 Jan 2002
This exhibit, part of K.M. Leytham's pre-filed testimony in PCHB No. 01-160, shows photographs taken on January 28, 2002, documenting standing water on top of a fill embankment near South 160th Street. The images provide visual evidence of water pooling conditions on the embankment surface, likely related to construction or environmental concerns associated with Sea-Tac Airport development. This material was submitted as part of a formal hearing record before the Pollution Control Hearings Board. -
2002-01-28
EXH AR026300: Exposed Fill Embankment S 160th St Slope Failure — Layering and Lack of Homogeneity, 28 Jan 2002
This exhibit, part of K.M. Leytham's pre-filed testimony (PCHB No. 01-160), shows a photograph taken on January 28, 2002, of an exposed fill embankment face near South 160th Street where a slope failure occurred. The image, approximately 4 feet high by 3 feet wide, reveals distinct layering and a lack of uniformity in the fill material. This evidence was submitted in connection with proceedings related to Sea-Tac Airport development and its surrounding infrastructure impacts. -
2002-01-28
EXH AR027041: Photographs by Peter Eglick During Site Visit on January 28, 2002
Photographs taken by Peter Eglick during a site visit on January 28, 2002, filed as part of the Administrative Record (AR 027041–027043). The images show ground-level views of a dark gravelly or paved surface with water pooling and streaking, possibly documenting stormwater, contamination, or site conditions at or near Sea-Tac Airport. -
2002-01-28
EXH AR026431: Absorbent Boom in Stream Below SDS1 Outfall — Turbid Effluent Photos, Jan 28, 2002
Two photographs taken by P. Willing on January 28, 2002, document an absorbent boom placed in a stream below the SDS1 outfall, a pollution-control measure used to contain contaminants. The second photo highlights turbid (murky) effluent visible in the stream, indicating water quality concerns at the site. These images appear to be part of an environmental monitoring or spill-response record associated with drainage infrastructure near Sea-Tac Airport. -
2002-01-24
EXH AR004637: Pre-Hearing Order — SHB No. 01-023, 01-024, 01-025 & 01-026 (Ecology v. Port of Grays Harbor, Mox Chehalis LLC, City of Westport)
Pre-Hearing Order issued by the Shorelines Hearings Board (SHB) in consolidated cases SHB No. 01-023, 01-024, 01-025, and 01-026. State of Washington Department of Ecology appellant; respondents are Port of Grays Harbor, Mox Chehalis LLC, and City of Westport; intervenors are Friends of Grays Harbor and Wildlife Forever of Grays Harbor. Appeals concern a proposed -
2002-01-23
EXH AR004654: Declaration of Jeff Kray — PCHB No. 01-160, ACC v. Ecology and Port Of Seattle
Declaration of Jeff Kray, Assistant Attorney General of Washington, Ecology Division, filed January 23, 2002 in PCHB No. 01-160 before the Pollution Control Hearings Board. Airport Communities Coalition (ACC) and Citizens Against Sea-Tac Expansion (CASE) are appellants against State of Washington Department of Ecology and Port Of Seattle. Attaches two documents: (1) Amended Final Findings -
2002-01-23
EXH AR004678: Port Of Seattle’s Reply Supporting Motion To Compel Document Production — ACC v. Ecology and Port Of Seattle, PCHB Case No. 01-160
Port Of Seattle’s reply brief supporting its motion to compel document production in Pollution Control Hearings Board Case No. 01-160, Airport Communities Coalition v. Department of Ecology and Port Of Seattle. Filed January 23, 2002. Port argues ACC has produced zero documents despite Port producing 22 boxes, 23 compact discs, and 4 hard diskettes. Port -
2002-01-23
EXH AR031469: Review of Third Runway Embankment Fill Monitoring Plan, 401 Certification Condition E.3, Port Of Seattle, November 2001
Internal memo from Ching-Pi Wang to Ann Kenny (cc: Jeannie Summerhays, Steve Alexander), dated January 23, 2002, reviewing the Port of Seattle’s Embankment Fill Monitoring Plan (EFMP) for the Third Runway, 401 Certification Condition E.3. Comments cover requirements for logic tree flow diagrams for tiered sampling and staged screening (groundwater, seepage), statistical methods for baseline -
2002-01-23
EXH AR022958: Wallula Power Project Site Certification Application Vol. 1 — Water Resources
This document is an Application for Site Certification for the Wallula Power Project in Washington State, submitted by Wallula Generation LLC to the State of Washington Energy Facility Site Evaluation Council. It details stormwater management plans for the 66-acre project site, including capturing rainfall and routing it through oil/water separators to a detention pond for reuse in the power plant's cooling tower. The application also addresses groundwater rights, noting that captured stormwater would reduce withdrawals from the gravel aquifer and Boise Cascade Corporation fiber farm wells.