TagACC(1534)
-
2001-07-26
EXH AR023796: Handwritten Meeting Notes — New LFM Proposal, Walker, NEPL, Storage, NRMP Impacts
Meeting notes from 2-26-01 discuss a new CFM proposal for Walker that may significantly increase storage requirements and affect SMP design feasibility, potentially impacting NRMP. Key concerns include the need to understand design feasibility and impacts, with discussion of resizing UDP to allow CFM regulations and hydrological monitoring. Participants noted too much time was being spent on modeling rather than addressing core design and impact questions. -
2001-07-25
EXH AR029221: Port Of Seattle Letter to Ecology on Low Streamflow Analysis, Summer Low Flow Impact Offset Facility, STIA
Letter dated July 25, 2001 from Keith R. Smith, Water Resources Manager, Port Of Seattle, to Ann E. Kenny, Washington Department of Ecology Northwest Regional Office, clarifying the Low Streamflow Analysis and Summer Low Flow Impact Offset Facility Proposal for Seattle-Tacoma International Airport. Corrections address: embankment recharge calculation using ‘flat outwash grass’; non-contiguous groundwater contributions -
2001-07-24
EXH AR029208: 401 Permit Decision-Making, Sea-Tac Airport Third Runway — Final Meeting Notes, Low Flow Analysis
Final meeting notes from July 24, 2001 conference call on 401 Permit Decision-Making for Sea-Tac International Airport Third Runway, Low Flow Analysis. Prepared by Kate Snider, Floyd & Snider Inc. Attendees included Ann Kenny (Dept. of Ecology), Kelly Whiting (King County), Keith Smith (Port of Seattle), Paul Fendt (Parametrix), Joe Brascher (Aquaterra). Discusses Port of -
2001-07-24
EXH AR050691: Installation and Verification Results, Work Area 2 Stone Column Test Areas, Third Runway Embankment Phase 4, Sea-Tac, Washington
Hart Crowser report (project 4978-44) prepared for HNTB documenting installation and verification results for Work Area 2 stone column test areas at the Third Runway Embankment Phase 4, SeaTac, Washington. Authored by Barry S. Chen, Ph.D., P.E. (Senior Associate Geotechnical Engineer) and John P. Laplante (Senior Staff Geotechnical Engineer). Report covers four test areas with -
2001-07-23
EXH AR051729: Low Flow Analysis – Flow Impact Offset Facility Proposal, Sea-Tac Airport
Port of Seattle letter dated July 23, 2001 to Ann E. Kenny, Washington State Department of Ecology, Northwest Regional Office, summarizing low streamflow impact analysis and flow impact offset facility proposal for Seattle-Tacoma International Airport Master Plan Update projects. Prepared by Parametrix, Inc. Analysis covers summer low streamflow impacts to Des Moines Creek, Miller Creek, -
2001-07-23
EXH 235: Follow-up Comments Low Streamflow Analyses — ACC Letter to Ecology
In a July 2001 letter to the Washington State Department of Ecology, Northwest Hydraulic Consultants raised concerns on behalf of the Airport Community Coalition that the Port of Seattle's ongoing low streamflow analyses for Des Moines, Walker, and Miller Creeks near Sea-Tac Airport were likely underestimating the airport's impact on local waterways. The consultants argued that the models were poorly calibrated for upper-basin conditions and failed to account for post-1994 improvements to the Industrial Wastewater System or the future loss of forested areas due to planned airport development. They requested that a final report on the streamflow analysis and any proposed mitigation measures be made available for public comment before Ecology used it to make its 401 Certification decision. -
2001-07-23
EXH AR029214: Port Of Seattle Low Streamflow Analysis and Summer Low Flow Impact Offset Facility Proposal, Sea-Tac Airport
Letter dated July 23, 2001 from Port Of Seattle to Ann E. Kenny at Washington State Department of Ecology Northwest Regional Office regarding Low Streamflow Analysis and Summer Low Flow Impact Offset Facility Proposal for Seattle-Tacoma International Airport. Covers summer low streamflow impacts in Des Moines Creek, Miller Creek, and Walker Creek from airport Master -
2001-07-23
EXH AR050780: Assessment of the Existing and Future Hydrologic Divide of Miller, Walker, and Des Moines Creeks After Construction of Master Plan Update Projects at STIA
Parametrix, Inc. report prepared for Port Of Seattle assessing the existing (1994) and future (2006) hydrologic divide of Miller Creek, Walker Creek, and Des Moines Creek following Master Plan Update (MPU) construction at Seattle-Tacoma International Airport (STIA). Analyzes compliance with Governor’s Certification requirement that the third runway project will not cause changes in the location -
2001-07-19
EXH AR018498: Port Of Seattle Parcel 92 Condemnation — Prior Converted Croplands Wetland Ruling and Lora Lake Mitigation Credit Discussion
Email chain (AR018498–AR018499) dated July 19, 2001, from Erik Stockdale (likely Washington State Department of Ecology) to Joan Marchioro (ATG) and Andy McMillan, forwarding a message from Jim Kelley of Parametrix, Inc. The judge ruled in favor of Port Of Seattle in the Parcel 92 condemnation case, finding that prior converted croplands were wetlands under -
2001-07-18
EXH AR021192: Supplemental Info Letter Stormwater BMP Performance Flow Augmentation STIA Sec 404 Permit App
A water resources consultant raised concerns in a July 2001 letter to the U.S. Army Corps of Engineers and Washington State Department of Ecology about the Port of Seattle's stormwater management plans for Sea-Tac Airport expansion. The letter challenged the effectiveness of proposed biofiltration swales, noting they can actually increase bacterial levels rather than reduce them, and warned that releasing stored stormwater from detention vaults into nearby Class AA streams could discharge pollutant-laden, oxygen-depleted water into already stressed waterways. The consultant concluded that the Port's plans fell short of providing reasonable assurance that water quality standards would be met.