2000-12-19
EXH 265: Comprehensive Stormwater Management Plan Agency Review — STIA Master Plan Update Improvements
This December 2000 Comprehensive Stormwater Management Plan, prepared by Parametrix, Inc. for the Port of Seattle, outlines how Seattle-Tacoma International Airport planned to manage stormwater runoff as part of its Master Plan Update improvements. The plan covers water quantity and quality standards, drainage basin conditions, hydrologic modeling, and best management practices for both existing and future airport development areas. It addresses topics such as detention storage, treatment of industrial wastewater, wildlife safety near detention ponds, and protection of nearby waterways including Miller Creek and Des Moines Creek. -
2000-12-14
Puget Sound Water Quality Management Plan 2000
The 2000 Puget Sound Water Quality Management Plan, adopted December 14, 2000, outlines coordinated local, state, tribal, and federal actions to restore and protect the health of Puget Sound in Washington State. The plan introduces new programs addressing aquatic nuisance species and Georgia Basin water coordination, while substantially revising existing stormwater, habitat, and wetlands protection programs. It builds on earlier management plans dating back to 1987 and calls for renewed commitment to funding and policy improvements. -
2000-12-08
EXH AR018814: Sea-Tac Airport Third Runway 401 Permit Negotiations — Meeting Notes Summary, October 2–December 8, 2000
This document summarizes technical negotiation meetings held between October and December 2000 regarding a 401 Water Quality Permit for the Port of Seattle's proposed third runway construction at Sea-Tac Airport. The discussions focused on resolving stormwater management issues, including detention pond sizing, basin hydrology, wetland impacts, and compliance with environmental regulations. A master list of technical issues was maintained jointly by the Port and the Washington State Department of Ecology to track the resolution status of each item prior to permit issuance. -
2000-12-08
EXH AR029061: Sea-Tac Airport Third Runway 401 Permit Negotiations Meeting Notes Summary – Draft for Review
Floyd & Snider Inc. meeting notes summary (draft for review) covering 401 Permit negotiations between the Port Of Seattle and Washington State Department of Ecology (Ecology) regarding the Sea-Tac Airport Stormwater Master Plan Update and third runway construction, October 2 through November 29, 2000. Document ECY00009383/AR029061 covers technical issues including detention sizing, basin acreage discrepancies, -
2000-12-08
EXH AR029087: Sea-Tac Airport Third Runway 401 Permit Negotiations — Final Draft Meeting Notes, December 8, 2000
Final draft meeting notes prepared by Kate Snider of Floyd & Snider Inc. from the Sea-Tac Airport Third Runway 401 Permit Negotiations meeting held December 8, 2000. Attendees included representatives from Washington State Department of Ecology (Ray Hellwig, Kevin Fitzpatrick, Ann Kenny, Dave Garland), Port Of Seattle (Elizabeth Leavitt, Michael Cheyne, Keith Smith), King County -
2000-12-08
EXH AR029093: Sea-Tac Airport Third Runway 401 Permit Negotiations Meeting Notes Summary, October–December 2000
Floyd & Snider Inc. meeting notes summary covering Sea-Tac Airport Third Runway 401 Permit negotiations between Port Of Seattle and Washington State Department of Ecology (Ecology), October 2 through December 8, 2000. Documents master list of 401 Permit technical issues including Stormwater Master Plan detention sizing, basin acreage discrepancies, HSPF and KCRTS hydrological models, IWS -
2000-12-08
EXH AR029120: Sea-Tac Airport Third Runway 401 Permit Negotiations — Meeting Notes Summary (Wetland Issues Only), October–December 2000
Floyd & Snider Inc. meeting notes summary covering 401 Permit negotiations between Port Of Seattle and Washington State Department of Ecology (Ecology) regarding the Sea-Tac Airport Third Runway and Stormwater Master Plan Update, October 2 through December 8, 2000. Document covers wetland issues only and includes a master list of 401 technical issues with resolution -
2000-12-01
EXH AR043961: Port Of Seattle Seattle-Tacoma Airport Master Plan Update Low Streamflow Analysis
Low Streamflow Analysis prepared by Earth Tech, Inc. for Port Of Seattle as part of the Seattle-Tacoma Airport Master Plan Update, dated December 2000. AR 043961. Report covers existing streamflow conditions, watershed modeling of current and proposed conditions, hydrologic behavior of runway fill, changes in non-hydrologic flows, effects of secondary recharge, reserved stormwater release, and -
2000-12-01
EXH AR021132: Comprehensive Stormwater Management Plan — Master Plan Update Improvements, STIA
This December 2000 report by Parametrix, Inc. for the Port of Seattle presents a Comprehensive Stormwater Management Plan for Master Plan Update improvements at Seattle-Tacoma International Airport. It maps the airport's drainage basins, surrounding watersheds (including the Duwamish River, Des Moines Creek, and Miller Creek watersheds), and identifies pollution-generating and non-pollution-generating surfaces across the airport property. The plan outlines water quality treatment strategies for existing and proposed impervious surfaces to manage stormwater runoff from airport operations. -
2000-12-01
EXH AR046366: Comprehensive Stormwater Management Plan — STIA Master Plan Update Improvements
Comprehensive Stormwater Management Plan (SMP) prepared by Parametrix, Inc. for the Port of Seattle, Seattle-Tacoma International Airport (STIA) Master Plan Update Improvements, December 2000, project number 556-2912-001(28). Document includes a July 2001 preface with replacement pages developed in response to Washington State Department of Ecology (Ecology) comments on Volumes 1 through 4. Covers stormwater management,