TagACC(1534)
-
2001-08-03
EXH 1268: King County DNR Letter to Ecology STIA Comprehensive Stormwater Management Plan
In August 2001, King County's Department of Natural Resources wrote to the Washington Department of Ecology confirming that the Port of Seattle's Comprehensive Stormwater Management Plan for Sea-Tac International Airport Master Plan improvements met the technical requirements of the 1998 King County Surface Water Design Manual. The review found that the plan demonstrated a feasible conceptual strategy for managing stormwater from proposed airport construction projects. Reviewers noted that while the plan showed compliance with design standards, additional oversight and monitoring would be needed as individual projects moved from planning into construction. -
2001-08-03
EXH AR050909: King County Review Comments on Port Of Seattle Low Flow Impact Analysis – Flow Impact Offset Facility Proposal, July 2001
Letter dated August 3, 2001 from King County Department of Natural Resources Director Pam Bissonnette to Ann Kenny, Senior Permit Specialist, Washington Department of Ecology Northwest Regional Office, transmitting King County’s technical review comments on the Port Of Seattle’s Low Flow Impact Analysis – Low Flow Impact Offset Facility Proposal (July 2001). The enclosure provides -
2001-08-03
EXH AR023795: PDA Request Low Flow Analysis — Helsell Fetterman to Ecology
In this August 3, 2001 email, Andrea Grad, a paralegal at Helsell Fetterman, submits a Public Disclosure Act (PDA) request to Ann Kenny at the Washington State Department of Ecology. Grad notes that several sections of the Port of Seattle's two-volume Low Flow Analysis — including the Introduction and the section on Determination of Impacts to Streamflow — were either incomplete or entirely missing from the copy provided by Ecology. She asks Ecology to confirm whether the Port had submitted the missing sections, and requests copies of any such materials. -
2001-08-02
EXH AR017713: Draft 401 Conditions to Address Potential Pathways — Deliberative, Do Not Disclose
Internal email from Ann Kenny (Ecology) to Ching-Pi Wang, cc Steve Alexander (ECY) and Raymond Hellwig, dated August 2, 2001, transmitting deliberative draft Section 401 water quality certification conditions F1–F4 for the Sea-Tac Airport (STIA) Third Runway Master Plan Update. Conditions address prevention of contaminated groundwater transport from the Airport Maintenance and Operations Area via -
2001-08-02
Exhibit 96: Email — Briefing Material for Governor on Sea-Tac 3rd Runway Project
Email from Dianne Pastore, Ecology Director’s Office, to Raymond Hellwig and Curt Hart (cc: Thomas Fitzsimmons, Sheryl Hutchison) requesting briefing materials for Tom Fitzsimmons’ meeting with the Governor and Paul Isaki on the SeaTac 3rd Runway Project. Materials requested by Dennis Clark, Governor’s Office, by COB Tuesday August 7, 2001. AR 017821, Exhibit 96. -
2001-08-02
EXH AR022933: Review Comments – Low Flow Impact Analysis & Offset Facility Proposal, Jul 2001
This August 2001 King County review evaluates the Port of Seattle's Low Flow Impact Analysis and proposed Flow Impact Offset Facility, which aims to mitigate reductions in stream flows in local creeks—including Des Moines, Miller, and Walker creeks—caused by future airport development. The review finds that while the proposed water storage and augmentation measures substantially offset low-flow impacts during the critical late-summer period, there are significant gaps in documentation, biological assessment, and design details that need to be addressed. Recommendations include professional engineering certification, enhanced biological monitoring, improved calibration documentation, and refinements to the reserve storage facility designs. -
2001-08-01
EXH AR017820: Email Chain — Ecology Internal Communications on Third Runway Decision Announcement Strategy
Internal email chain dated August 1, 2001 among Washington Department of Ecology staff Thomas Fitzsimmons, Sheryl Hutchison, Dianne Pastore, and Raymond Hellwig regarding communications strategy around the Sea-Tac Airport third runway decision. Topics include scheduling media availability, coordinating with the governor and Isaki, Port Commission meeting on August 14, E-Board contact timing, press attendance at -
2001-08-01
Exhibit 149: Draft 401 Conditions — Auburn Mitigation Site Revisions and Performance Standards
Deliberative memorandum dated August 1, 2001, from Katie Walter to Ann Kenny, Washington State Department of Ecology, re Draft 401 Conditions for the Auburn Mitigation Site. Covers culvert placement issues in the revised grading plan (June 28, 2001) including northwest corner drainage swale culvert (approximately 60 feet long), south central mis-located culvert, and two additional -
2001-08-01
EXH AR053462: Stormwater Management Manual for Western Washington (Volumes I–V)
Washington State Department of Ecology Water Quality Program publication numbers 99-11 through 99-15, August 2001. Stormwater Management Manual for Western Washington covering five volumes: Volume I Minimum Technical Requirements and Site Planning, Volume II Construction Stormwater Pollution Prevention, Volume III Hydrologic Analysis and Flow Control Design/BMPs, Volume IV Source Control BMPs, Volume V Runoff Treatment -
2001-08-01
EXH AR018500: Draft 401 Conditions — Auburn Mitigation Site Revisions and Performance Standards
Deliberative memorandum dated August 1, 2001 from Katie Walter (KLW@shanwil.com) to Ann Kenny, Washington State Department of Ecology, re Draft 401 Conditions for Auburn Mitigation Site revisions. Covers culvert placement issues in revised grading plan (June 28, 2001) at northwest corner and south central portion of site, drainage swale, maintenance pathway, and southwestern basin. Performance