TagInterlocal Agreement(170)
-
2019-02-06
City of Burien Invoice #568: Interlocal Agreement Contract #18-A101 SAMP Payment #2
This is an invoice dated February 6, 2019, from the City of Burien to the City of Des Moines, billing $601.80 for the second payment under an interlocal agreement (Contract #18-A101) related to the South Airport Mitigation Program (SAMP) for the period of October 1 through December 31, 2018. The invoice, numbered 568, was due by March 8, 2019, and reflects a cost-sharing arrangement between the two cities for coordinated noise mitigation efforts connected to Sea-Tac Airport. Payment was to be remitted to the City of Burien Finance Department in Burien, Washington. -
2019-01-25
City of Burien Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
In 2018, the cities of Burien, Des Moines, Normandy Park, and SeaTac entered an Interlocal Agreement to jointly hire the law firm Lockridge Grindal Nauen PLLP for a total of $175,000 to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), with costs split among the cities based on population at approximately $1.50 per capita. The document includes billing records showing two invoices totaling $64,916.83 billed to date, covering legal research on topics such as airport noise programs, Part 150 noise studies, and community engagement strategy. Burien served as the fiscal manager, with each city's share proportional to its population — for example, Burien (51,000 residents) owed 42.97% of the total contract cost. -
2019-01-25
City of Burien Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
In 2018, the cities of Burien, Des Moines, Normandy Park, and SeaTac entered an Interlocal Agreement to jointly hire the law firm Lockridge Grindal Nauen PLLP for a total of $175,000 to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), with costs split among the cities based on population at approximately $1.50 per capita. The document includes billing records showing two invoices totaling $64,916.83 billed to date, covering legal research on topics such as airport noise programs, Part 150 noise studies, and community engagement strategy. Burien served as the fiscal manager, with each city's share proportional to its population — for example, Burien (51,000 residents) owed 42.97% of the total contract cost. -
2019-01-25
City of Burien Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington entered into an Interlocal Agreement with Des Moines, Normandy Park, and SeaTac to jointly review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), hiring law firm Lockridge Grindal Nauen PLLP for environmental review consulting at a total contract value of $175,000. Each city's share of costs was calculated at approximately $1.50 per capita, with Burien responsible for the largest share at 42.97%. As of the second invoice dated January 25, 2019, covering services through December 31, 2018, a total of $64,916.83 had been billed, with $110,083.17 remaining on the contract. -
2019-01-25
City of Burien Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
The City of Burien, Washington entered into an Interlocal Agreement with Des Moines, Normandy Park, and SeaTac to jointly review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), hiring law firm Lockridge Grindal Nauen PLLP for environmental review consulting at a total contract value of $175,000. Each city's share of costs was calculated at approximately $1.50 per capita, with Burien responsible for the largest share at 42.97%. As of the second invoice dated January 25, 2019, covering services through December 31, 2018, a total of $64,916.83 had been billed, with $110,083.17 remaining on the contract. -
2019-01-25
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
In 2018, the cities of Burien, Des Moines, Normandy Park, and SeaTac entered an Interlocal Agreement to jointly hire the law firm Lockridge Grindal Nauen PLLP for $175,000 to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), with each city's share based on a per-capita funding rate of approximately $1.50. Two invoices totaling roughly $64,917 had been billed by January 2019, covering legal research into airport noise programs, Part 150 noise studies, and community engagement strategies. The remaining contract balance of approximately $110,083 was still outstanding as of that date. -
2019-01-25
Billing Backup for City Shares of Lockridge Grindal Nauen Invoices for Sea-Tac Airport SAMP Review
In 2018, the cities of Burien, Des Moines, Normandy Park, and SeaTac entered an Interlocal Agreement to jointly hire the law firm Lockridge Grindal Nauen PLLP for $175,000 to review the Sea-Tac Airport Sustainable Airport Master Plan (SAMP), with each city's share based on a per-capita funding rate of approximately $1.50. Two invoices totaling roughly $64,917 had been billed by January 2019, covering legal research into airport noise programs, Part 150 noise studies, and community engagement strategies. The remaining contract balance of approximately $110,083 was still outstanding as of that date. -
2018-11-05
Agreement Between the Cities of Burien, Des Moines, Normandy Park, Federal Way, Tukwila, and Sea-Tac to Provide Local Matching Funds for the Sea-Tac Airport Impact Study
Six cities near Seattle-Tacoma International Airport — Burien, Des Moines, Federal Way, Normandy Park, Tukwila, and SeaTac — agreed to jointly contribute $300,000 in local matching funds to unlock an equal amount of state funding for a study of the airport's current and ongoing impacts on surrounding communities. Under the agreement, the City of SeaTac serves as the fiscal and contracting agent, collecting contributions from the other cities and transferring the combined funds to the Washington State Department of Commerce, which will hire a consultant to conduct the study. The agreement outlines each city's financial obligations, dispute resolution procedures, and the process for participating in and reviewing the study's draft findings. -
2018-10-31
City of Burien Invoice #466: SAMP Payment #1 to City of Sea-Tac
The City of Burien billed the City of SeaTac $15,331.10 for the first payment under an interlocal agreement (Contract #18-A101) related to the SeaTac Airport Mitigation Program (SAMP), covering work performed between July 23 and September 25, 2018. The invoice, numbered 466 and dated October 31, 2018, was addressed to SeaTac planning official Steve Pilcher and was due by November 30, 2018. This document reflects a cost-sharing arrangement between the two cities for airport noise policy and mitigation planning efforts. -
2018-10-31
City of Burien Invoice #466: SAMP Payment #1 to City of Sea-Tac
The City of Burien billed the City of SeaTac $15,331.10 for the first payment under an interlocal agreement (Contract #18-A101) related to the SeaTac Airport Mitigation Program (SAMP), covering work performed between July 23 and September 25, 2018. The invoice, numbered 466 and dated October 31, 2018, was addressed to SeaTac planning official Steve Pilcher and was due by November 30, 2018. This document reflects a cost-sharing arrangement between the two cities for airport noise policy and mitigation planning efforts.