Notes
Hart Crowser, Inc. subsurface conditions data report (project 4978-28) prepared for HNTB, dated September 21, 2001, covering Phase 5 Fill and Subgrade Improvement for the Third Runway Embankment at Sea-Tac International Airport, SeaTac, Washington. Report authored by Carsten Becker (E.I.T., Senior Staff Geotechnical Engineer) and Michael J. Bailey (P.E., Project Manager). Covers geologic and hydrogeologic conditions in Work Area West, Work Area South 1, Work Area South 2, Pond D, and Pond F; includes water level data, hydraulic conductivity, soil conditions, and test pit summaries for stockpiles. AR 051257.