Notes
Email from Andy McMillan (SEA program) dated June 12, 2000, forwarded by Tom Luster to Raymond Hellwig on October 6, 2000, transmitting the official version of a Word document titled “Lessons Learned from Big Projects: Recommendations for SEA Program.” The attached document outlines 7 recommendations developed from SEA program staff experiences with large, complex projects including Crown Jewel Gold Mine, Sea-Tac Third Runway, 304th Street Landfill, and Arrowleaf. Recommendations cover workload management, preventing applicant end-arounds of project staff, project decision-making guidance when staff disagree with agency decisions, broad public input throughout project review, documentation and peer review requirements, agency-wide coordination process for large projects, and SEA Program internal coordination. Document references Permit Assistance Center (PAC), SEPA section, PMT, and cost recovery program. AR 017776–017778.