Aviation Capital Planning & Preliminary Design Action Item: July 23, 2019

Port of seattle 2019 07 23 aviation capital planning preliminary design action item pdf

Notes

Port of Seattle Aviation Capital Planning & Preliminary Design Action Item presentation dated July 23, 2019 (Item No. 3c). Covers the airport project planning process across three phases: master planning (complete), advanced planning (in progress), and preliminary design (current capital funds request). Topics include near-term projects, projects requiring preliminary design, Glideslope Antenna Relocation, and next steps. Preliminary design phase produces a Project Definition Document (PDD) for individual projects at Sea-Tac Airport, including the Second Terminal curb and functional area configuration.

V V