Notes
Final Work Program Task Summary dated September 17, 1980 (D/WELLS/805/20) for the Noise Exposure Forecast Update at Sea-Tac International Airport. Document outlines six phases: Phase I (Scoping and Funding, including FAA-PGP Funding Grant Application), Phase II (INM Verification, including development of initial data base with NMS monitoring data, real-time flight track observation, INM input preparation, model verification), Phase III (Supplemental Data Compilation, including field data collection and noise system survey), Phase IV (Real-Time Forecasts, including operations growth estimation and land use survey), Phase V (INM Forecast Generation, Conclusions, and Report), and Phase VI (Administration and Citizen Involvement, including Technical Committee Interaction, Port Commission Action). Staff listed include Sims, Parks, Dohrmann, and Wells. References Aviation Safety and Noise Abatement Act of 1979 and Sea-Tac/Communities Plan.