Notes
Final meeting notes from July 16, 2001 for the 401 Permit Decision-Making process for Sea-Tac International Airport Third Runway, covering low flow analysis for Miller Creek and Walker Creek. Attendees included Ann Kenny (Dept. of Ecology), Kelly Whiting (King County), Keith Smith (Port of Seattle), Paul Fendt and Robert Farid (Parametrix), Rick Schaefer (EarthTech), and Joe Brascher (Aquaterra). Topics include proposed mitigation period August 1–October 31, mitigation flow rates of 0.10 cfs (Miller Creek) and 0.065 cfs (Walker Creek) using 1991 as the 2-year return frequency surrogate target year, reserve storage vault sizing (14 ac-ft, 5 vaults in Miller Basin, 92-day release at 0.10 cfs), non-hydrologic effects including septic tank removal under Section 401, biological impact questions raised by King County, and next steps including Port submittal by 7/23. Document marked AR 017658–017660.