Notes
Final draft meeting notes from a 401 Permit Decision-Making technical meeting on May 25, 2001, regarding the Sea-Tac International Airport Third Runway project. Prepared by Rachel McCrea of Floyd & Snider Inc. Attendees included Ann Kenny (Dept. of Ecology), Kelly Whiting (King County), Keith Smith (Port of Seattle), Paul Fendt and Tom Atkins (Parametrix). Topics covered: format for final SMP (Stormwater Management Plan) replacement pages, existing SMP text referencing low stream flow impacts and proposed mitigation (Appendix D, Appendix G, Table G-2), Table A-3 Deliverable 5 (yellow) clarification including 154th/156th facility retrofit and SDN2X/4X runway threshold removal, schedule update for deliverables D1–D9 including Miller Creek (D7A), 154th Street (D7B), Infiltration Feasibility (D4B), and dam safety information (D8). Deliverable 7A transitioned from Joe Brascher to Felix Kristanovich. AR029179, ECY00014855.