Floyd & Snider Inc. meeting notes summary covering 401 Permit negotiations between Port Of Seattle and Washington State Department of Ecology (Ecology) regarding the Sea-Tac Airport Third Runway and Stormwater Master Plan Update, October 2 through December 8, 2000. Document covers wetland issues only and includes a master list of 401 technical issues with resolution status. Key topics include detention sizing, basin acreage discrepancies, HSPF and KCRTS stormwater models, IWS pump station modeling, Des Moines Creek flow augmentation, Walker Creek calibration, wetlands 18/37/39B hydrology maintenance, Natural Resources Mitigation Plan (NRMP) consistency, Borrow Site #3, Tyee Pond, SR 509 interchange impacts, runway de-icing/dissolved oxygen study, Kludt settlement compliance, and King County off-site flow criteria. Administrative Record numbers AR 029120–AR 029122, ECY00012496–ECY00012498.