Email dated May 17, 2001 from Raymond Hellwig (Ecology) to Thomas Fitzsimmons and Tom Fitzsimmons, cc Ann Kenny, transmitting an ‘updated’ discussion paper marked deliberative and not yet available for public disclosure. The attached discussion paper (issuelink-1.doc) addresses three key issues carried forward from a September 2000 paper: (1) Stormwater Management Plan (SMP) led by Kelly Whiting, (2) Low Flow Mitigation (LFM) Plan involving base flow impact numbers for Des Moines Creek and Miller Creek, with Dave Garland assisting, and (3) Natural Resource Mitigation Plan (NRMP) led by Katie Walter with Shannon and Wilson. The paper discusses Port Of Seattle’s need to use stormwater to mitigate flows in DM and Miller Creeks, problems with double-counted rain, embankment infiltration estimates, and the interdependency of SMP, LFM, and NRMP. AR 017794, DOES 13:01 0769–0770.