In September 2012, the Port of Seattle Commission considered a $6 million request to create a new Sustainability Master Plan (SMP) for Seattle-Tacoma International Airport, replacing an outdated 15-year-old plan. The update was driven by nearly 50% passenger growth since the last plan, rising capacity pressures on roadways, terminals, and taxiways, and the need to meet FAA requirements for federal grants and environmental permits. The SMP aimed to guide long-term airport development through 2015, balancing future growth with sustainability goals within the airport's existing footprint.

Notes

Port of Seattle memorandum requesting $6.0 million authorization to create an Airport Sustainability Master Plan for Seattle-Tacoma International Airport. The existing master plan is 15 years old and needs replacement due to 50% passenger growth since the last study was completed.