Notes
Exhibit AR018609. December 18, 1996 letter from Barbara Hinkle, Senior Environmental Specialist, Port Of Seattle, to Jack Kennedy, U.S. Army Corps of Engineers Seattle District Office, submitting a Section 404 application to place fill material into waters of the United States at Seattle-Tacoma International Airport for Master Plan Update improvements. Details wetland impacts: Third Parallel Runway 7.38 acres, Runway Safety Areas (16L/R) 2.34 acres, Terminal/Landside improvements 2.51 acres (South Aviation Support Area and North Employee Parking Lot), subtotal 12.23 acres. References February 1996 FAA/Port of Seattle joint NEPA/SEPA Final EIS, PSRC Resolution A-93-03, Resolution EB-94-01, Resolution A-96-02, Puget Sound Air Transportation Committee (PSATC), Flight Plan Study, and PSRC Expert Panel findings. Discusses poor weather operating constraints, VFR/IFR arrival delays, $42 million annual delay costs under 1992 demand, and projected $176 million at 425,000 annual operations. Third runway located 2,500 feet west of existing 16R/34L.