Notes

Draft geotechnical engineering report prepared by Hart Crowser, Inc. for HNTB regarding the Third Runway Embankment, Phase 5 at Sea-Tac International Airport, SeaTac, Washington (project no. 4978-28, AR 052045). Authored by Josepha D. Celes (Senior Staff Geotechnical Engineer) and Michael Bailey, P.E. (Project Manager). Covers site preparation, subgrade improvement, embankment fill construction, TESC Pond A, subsurface soil and groundwater conditions in Work Area West and Work Area South 2, soil gradations for embankment fill material groups, sheet pile barriers, and mechanically stabilized earth.