Notes
Port of Seattle SEPA addendum (POS SEPA No. 01-05, AR 049967) dated March 6, 2001, for the Seattle-Tacoma International Airport North Electric Service Upgrade project. Documents a revised proposal for the North Main Service Point site location and 12.5 kV cable route connecting to the Bow Lake Substation via International Boulevard near South 176th Street. Addresses land use, aesthetics, and transportation impacts including temporary lane closures on airport roadways, underground ductbank installation between the North Main Service Point and Airport electric circuits, and traffic control measures. Port of Seattle determined the revised proposal is a minor change within the scope of the original North Electric Service Upgrades project with no significant adverse impacts.