Notes
Letter dated September 28, 2000 from Tom Fitzsimmons, Director of Washington State Department of Ecology, to M.R. (Mic) Dinsmore, Executive Director of Port Of Seattle, responding to Port Of Seattle’s withdrawal of its Clean Water Act § 401 Water Quality Certification application for the Third Runway project at Seattle-Tacoma International Airport. Ecology outlines conditions for future § 401 Certification approval including stormwater management plan (SMP) revisions addressing deficiencies identified by King County review, flow control for Miller Creek, Walker Creek, and Des Moines Creek, protection of Tyee Pond, excavation of Borrow Site #3, Hydraulic Project Approvals from Department of Fish and Wildlife, and consistency with the Natural Resources Mitigation Plan (NRMP). Ecology commits to completing review within sixty days upon Port reapplication. AR018381–AR018383.