Notes
The Port of Seattle submitted a Section 404 Application to the U.S. Army Corps of Engineers to place fill material into waters of the United States at Seattle-Tacoma International Airport as part of the Master Plan Update improvements. The letter provides background on the nearly ten-year regional planning process, including the Flight Plan Study and PSRC approvals, culminating in the Port Commission’s August 1996 approval. It outlines wetland impacts totaling 12.23 acres associated with the Third Parallel Runway, Runway Safety Areas, and terminal/landside improvements, and justifies the third runway as the best solution for addressing poor weather operating constraints.