Sound Transit update: Highline Forum

A November 2021 Sound Transit update presented to the Highline Forum outlines plans to open 28 new light rail stations by 2024, including extensions to Federal Way, Lynnwood, East Link, and other corridors in the greater Seattle region. The presentation also addresses a financial affordability gap, explaining that some projects have two possible delivery dates — an earlier target date contingent on securing additional funding, and a later affordability date if extra financial capacity cannot be achieved.

Notes

A Sound Transit presentation to the Highline Forum on November 17, 2021, outlining 28 new light rail stations planned by 2024 across multiple extensions including Northgate, Hilltop Tacoma, East Link, Lynnwood, Federal Way, and Downtown Redmond. The presentation also covers the board’s decision to ‘realign’ project schedules to address an affordability gap, resulting in dual Target and Affordability delivery dates for four projects.

V V