Notes
Weekly Project Progress Report dated 25 April 1997 for the Sea-Tac Impact Mitigation Study (HOK Project #96-0154-802), submitted by Joseph A. Pobiner, AICP, of Hellmuth, Obata + Kassabaum, Inc. (HOK), Dallas. Covers period 21-25 April 1997. Distributed to Fred Stouder (City of Burien), Donal Simpson (HOK/Dallas), Dennis Cope (HOK/Seattle), Gerry Tunnell (Raytheon), Steve Dennis (Raytheon), Ron DeNadai (STV), Ted Lane (Thomas/Lane), and Mike McCormick. Tasks 1-6 are 100% complete; Task 7 (Socio-Economic Analysis) to be completed by Thomas/Lane Associates under separate contract with City of Burien; Task 8 (Mitigation Plan) at 99%; Project Total at 99%. Accompanied by a cover letter dated 29 April 1997 with scheduling suggestions for Burien meetings 5-15 May 1997, including Citizens Brown Bag meetings, Burien City Council meetings, public meetings, and State and Federal Agencies Technical Group meeting. Also references a PowerPoint presentation draft for the SeaTac Area Mitigation Study.