Email dated May 19, 2000 from Raymond Hellwig (City of Des Moines) to Thomas Fitzsimmons regarding the SeaTac 3rd Runway permitting process. Discusses tight July 2000 decision-making timeframe, King County review of Port Of Seattle stormwater management plan requiring up to 10 more weeks, development of a definitive issues list for the proposed runway, drafting 401 language, internal staff meetings, weekly progress reports, and managing workload from ‘background buzz’ including public records requests from opponent groups. Handwritten annotation reads ‘not used but permit made’ with reference ‘167 1-18-2002 Fitzsimmons’. AR 018380.