Peat, Marwick, Mitchell & Co. October 1981 project schedule (Gantt chart, Exhibit 1) for the Airspace Study covering Sea-Tac International Airport and King County International Airport. Charts nine tasks including Prepare Study Design, Document Study Background, Conduct Inventory, Prepare Forecasts, Conduct Preliminary Analysis of Airspace Interactions, Review and Report Production, Conduct Detailed Analysis of Airspace Interactions, Evaluate Alternatives, Prepare Draft Report, and Final Report Production. Task 8 covers Project Coordination and Public Participation Program with advisory committee meetings and public information meetings. Project runs 13 months across Phase 1 and Phase 2.