Declaration of Michael Cheyne, Port Of Seattle project manager for the Sea-Tac third runway construction, filed in PCHB case No. 01-133 (Airport Communities Coalition v. Department of Ecology and Port Of Seattle). Cheyne describes his role overseeing administration, planning, design, and construction of the Sea-Tac third runway as part of the Master Plan Update (MPU). States that a stay would halt fill material discharge into waters of the United States, limiting activity to property acquisition, fill stockpiling, airfield improvements, and wetland mitigation site development. Identifies impacts to Phase 5 embankment project and relocation of South 154th Street, with a projected one-year delay and financial consequences of up to $49,000 per day or $17,000,000 per year on the $493 million project (inflated at 3.5% annually). Filed by Foster Pepper & Shefelman PLLC.