This slide from the Seattle-Tacoma International Airport Sustainable Airport Master Plan presents the planning schedule, including Activity Forecast (completed Q3 2014), Alternatives Analysis & Plan Development (Q4 2014–Q3 2015), Program Plan of Finance (Q1 2016), and Environmental Review (Q3 2015–Q4 2016). A Gantt chart at the bottom shows task timelines across 2014–2016, with Commission Briefing milestones marked.

Notes

This slide from the Seattle-Tacoma International Airport Sustainable Airport Master Plan presents the planning schedule, including Activity Forecast (completed Q3 2014), Alternatives Analysis & Plan Development (Q4 2014–Q3 2015), Program Plan of Finance (Q1 2016), and Environmental Review (Q3 2015–Q4 2016). A Gantt chart at the bottom shows task timelines across 2014–2016, with Commission Briefing milestones marked.