A budget table showing five line items related to Baggage Optimization phases and a CCE Transfer Line, with a total budget of $955,000,000 against a current estimate of $1,074,638,982, resulting in a 13% over-budget variance of $119,638,982. The largest overage is Baggage Optimization Phase 3, which exceeds its budget by $153,050,000.Open full document
Notes
A budget table showing five line items related to Baggage Optimization phases and a CCE Transfer Line, with a total budget of $955,000,000 against a current estimate of $1,074,638,982, resulting in a 13% over-budget variance of $119,638,982. The largest overage is Baggage Optimization Phase 3, which exceeds its budget by $153,050,000.