Sustainable Airport Master Plan Near-Term Projects Environmental Review: Additional Contract Authorization

2026 03 24 rm 8j presentation SAMP ntp environmental review agreement 1 pdf

Notes

Port Of Seattle Commission presentation (Item 8j supp) dated March 24, 2026 requesting $1,000,000 additional contract authorization for the Sustainable Airport Master Plan (SAMP) Near-Term Projects Environmental Review. Total authorizations including this request reach $9,750,000, following previous authorizations of $3,000,000 (11/10/2015), $3,400,000 (2/25/2021), and $2,350,000 (6/27/2023). Budget increase justified by enhanced outreach and engagement in NEPA and SEPA, additional analyses for the Draft State Environmental Policy Act (SEPA) Environmental Impact Statement (EIS), and administrative contract cost escalations.

V V