StART SIRRPP Update: Field Assessment and Acoustic Testing of 30 Homes — Slide 9 (February 26, 2025)

A presentation slide states that third-party consultants conducted field assessment and acoustic testing concurrently at 30 homes over a two-week period beginning August 19, 2024. The 30 homes were selected to reflect the distribution of manufacturers by year for sound insulation packages installed between 1986 and 2014.

Notes

A presentation slide states that third-party consultants conducted field assessment and acoustic testing concurrently at 30 homes over a two-week period beginning August 19, 2024. The 30 homes were selected to reflect the distribution of manufacturers by year for sound insulation packages installed between 1986 and 2014.