Notes
Port Of Seattle presentation dated May 22, 2024, updating the Sound Insulation Repair and Replacement Pilot Program (SIRRPP) at Sea-Tac Airport. Covers Commission Order 2024-04 (approved February 27, 2024), which established the pilot program with a total authorized budget of $6.5M ($5M for design/construction), funded by tax levy, incorporating equity guidelines. Three assessment phases: Planning Phase, Study and Testing Phase, and Report Phase, with completion target by end of 2024. Schedule milestones include surveys mailed June 3/24 and July 15 (closing August 9), acoustic testing August 19/30, acoustic test report October 14, draft study report November 7, legal review November 22, final report approval December 23, and Commission Briefing January 21, 2025. Part 150 meetings June 5, 6, and 8 also noted.