EXH AR017771: Ecology Internal Email — May 16 Meeting with Port Of Seattle on Third Runway 401 and CZM Review

Notes

Raymond Hellwig (Washington State Department of Ecology) emails Joe Dear and colleagues on May 15, 2000, as an addendum to a memo preparing for a May 16 meeting with Port Of Seattle regarding the Sea-Tac Third Runway. Explains that the one-year 401 Water Quality Certification evaluation period restarted September 1999, with a possible July 2000 decision if Port Of Seattle submits adequate information. Critically, Port Of Seattle must withdraw and resubmit its Coastal Zone Management (CZM) consistency determination request before the June 8, 2000 deadline to avoid Ecology denying CZM consistency. Documents the administrative conflict between the one-year WQ 401 timeline and the six-month CZM timeline, and states Ecology is assuming Port Of Seattle will honor its verbal commitment to withdraw and resubmit the CZM request. AR 017771.