South 200th Link Extension Briefing: Sea-Tac City Council Briefing

This March 25, 2014 Sound Transit briefing document, presented to the SeaTac City Council, outlines the South 200th Link Extension project—a 1.6-mile elevated light rail extension from the SeaTac/Airport Station to a new Angle Lake Station, including a parking garage. The project was scheduled for construction between 2013 and 2016, with a planned opening for service in Fall 2016, and carried a total budget of $383.2 million.

Notes

Sound Transit and City of SeaTac presentation to the SeaTac City Council on March 25, 2014, covering the South 200th Link Extension project. The project is a 1.6-mile elevated guideway and station extension of Central Link with a parking garage, connecting from SeaTac/Airport Station to Angle Lake Station. Schedule includes Final Design 2013, Construction 2013-2016, system testing 6 months, and open for service Fall 2016 (includes 5 months of float). Project budget: $383.2 million.