Final decision on noise issues

Psrc 8108 air expert panel noise final decision 1996 03 pdf

Notes

The Expert Arbitration Panel on Noise and Demand/System Management Issues issued its final decision on noise issues related to Resolution A-93-03, which set noise reduction conditions for PSRC authorization of a third runway at Sea-Tac International Airport. A majority of the Panel found that the Port of Seattle had not demonstrated a sufficient reduction in real on-the-ground noise impacts to satisfy the resolution’s requirements, despite an impressive array of noise abatement and mitigation programs. The Panel Chair dissented, finding the Port had satisfied the requirements.

V V