The Port of Seattle's Capital Improvement Projects Third Quarter Report for 2018 provides a status update on 100 active capital projects managed by the Construction and Development Division (CDD) and Information and Communications Technology (ICT) department. Of those projects, 47 were on or ahead of schedule and budget, while 53 faced schedule or budget challenges, including 13 new reportable variances identified during the quarter. The report tracks project performance trends across multiple quarters, noting two new projects moved to critical (red) status and ten additional projects raised concerns (amber) in Q3 2018.Open full document
Notes
Port of Seattle Capital Improvement Projects Third Quarter Report for 2018, presented at the December 11, 2018 commission meeting. The report covers 100 total projects managed by CDD and ICT, with 47 projects on schedule and budget, 46 with either schedule or budget off target, and 7 with both off target. A corrected version was issued December 13, 2018 for slide 15.