2018 third quarter capital improvement projects report

A December 2018 Port of Seattle Commission briefing reported on the status of 100 Capital Improvement Projects managed by Aviation, Seaport, and Information Technology departments. Of those projects, 47 were on budget and on schedule, 46 were behind schedule, and 7 were both behind schedule and over budget. The report was prepared to meet Port of Seattle oversight requirements for major capital projects.

Notes

A briefing memorandum to the Port of Seattle Executive Director summarizing the status of Capital Improvement Projects for Q3 2018. The report covers 100 projects managed by Aviation, Seaport, and ICT departments, with 47 on budget/schedule, 46 behind schedule, and 7 behind schedule and over budget. Three projects were substantially completed this quarter.