Baggage optimization project update

The Port of Seattle's Baggage Optimization Project is replacing six individual baggage screening systems at Seattle-Tacoma International Airport with a single centralized system designed to handle up to 60 million passengers per year. Construction began in May 2017 and is being carried out in three phases, with full completion expected in 2025, at a total project budget of approximately $445 million. The project aims to increase baggage screening capacity, improve flexibility for passengers checking bags, and enhance overall energy efficiency within the airport's existing footprint.

Notes

This Commission briefing memorandum provides an update on the Port of Seattle’s Baggage Optimization project, which replaces six individual baggage screening systems with a centralized system designed to accommodate 60 Million Annual Passengers. The update covers Phase 1 construction progress, Phase 2 design negotiations, and the overall project schedule and budget of $445 million.