Notes
Declaration by Michael Cheyne, project manager for the Port of Seattle’s third runway construction at Sea-Tac Airport, submitted in Pollution Control Hearings Board case No. PCHB 01-133. Cheyne describes the construction schedule, his qualifications, and the significant financial and operational consequences of a stay being issued, including costs of up to $49,000 per day or over $17 million per year of delay.