The Port of Seattle's C800612 Baggage Optimization project replaces six separate baggage screening systems at Seattle-Tacoma International Airport with a single centralized system designed to handle up to 60 million passengers per year. Phase 1 construction began in May 2017, with the overall project expected to be completed by the second quarter of 2025.Open full document
Notes
This presentation provides a 2017 Q3 briefing on the C800612 Baggage Optimization project at Sea-Tac Airport. The project replaces six individual baggage screening systems with a centralized system designed to accommodate 60 million annual passengers. Phase 1 construction was underway as of the briefing, with overall project completion expected in Q2 2025.