This project timeline slide shows the environmental review schedule for what appears to be a Sea-Tac Airport noise or development project, marking the current position at the Draft SEPA EIS Publication date of 5/22/26. Key milestones include the Final NEPA FEA & Decision (9/26/25), a 60-day public review period, Final SEPA EIS & Decision in Q4 2026, and a 21-day appeal period, culminating in Commission Action Required for NTP(s) approval in 2027.Open full document
Notes
This project timeline slide shows the environmental review schedule for what appears to be a Sea-Tac Airport noise or development project, marking the current position at the Draft SEPA EIS Publication date of 5/22/26. Key milestones include the Final NEPA FEA & Decision (9/26/25), a 60-day public review period, Final SEPA EIS & Decision in Q4 2026, and a 21-day appeal period, culminating in Commission Action Required for NTP(s) approval in 2027.