The Port of Seattle requested a contract budget increase in February 2020 for the environmental review of near-term projects under the Sustainable Airport Master Plan at Sea-Tac Airport. The review process, which began with public and agency scoping in Fall 2018, was on track to produce a NEPA Environmental Assessment by October 2020 and a final SEPA Environmental Impact Statement decision by September 2021. Early accomplishments included a demand forecast update, constrained operating growth scenarios, and preliminary Purpose and Need documentation.Open full document
Notes
This presentation to the Port of Seattle Commission requests a contract budget increase for the environmental review of near-term projects under the Sustainable Airport Master Plan (SAMP). It outlines the project schedule from scoping in Fall 2018 through final NEPA EA and SEPA EIS decisions expected in 2021, and summarizes accomplishments including agency and public scoping, a scoping report, demand forecast updates, and preliminary Purpose and Need documentation.