FAA Slide: Milestone Summary and Dashboard Status, July 2012 As of June 30th 2012 Design Phase the project was a mere 25% complete. Basically, there wasn’t a design available on March 1st 2012 to analyze, which comports with the fact that in the schedule, the “Phase Start” (the actual EA analysis) starts on January 6th 2013, right after the final design report (from the Design and Develop Phase) was to be completed on Dec. 21, 2012.