2018 12 11 RM 9a supp

▪ 100 Total Projects in report (87 CDD, 13 ICT) ▪ 47 Projects are within or ahead of target schedule and budget ▪ 46 Projects have either target schedule or budget off with 11 new Reportable Variances for this Quarter. ▪ 7 Projects have both target schedule and budget off with 2 new Reportable Variances for this Quarter. ▪ 3 Projects are Substantially Complete Capital projects managed by CDD and ICT 4Q17 Report 1Q18 Report 2Q18 Report 3Q18 Report Series3 5 6 8 7 Series2 35 37 38 39 Series1 46 40 45 41 45 41 (Schedule) (Schedule) (Schedule) (Schedule) (budget) 8 7 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Off Schedule and Budget Off Schedule or Budget On Schedule and Budget Two new red and 10 new amber CDD Projects by Status, by Quarter CDD Projects by Dollar Value $683M $121M $2.18B $25M Total Budget = $3.03B $14M Off Schedule and Budget – OLD VARIANCE - Emergency Gen - $2.6 M - IWS Segregation Improvements - $1.1M - Electric Utility SCADA - $9.6M - Shilshole Bay Marina Paving - $2.0M - Shilshole Tenant Services Building - $10.1M Off Schedule and Budget – NEW VARIANCE - Telecommunications Meet Me Room - $3.9M - Wi-Fi Enhancement for Ramp and Term - $10.6M Off Schedule/Budget $25M or More – OLD SCHEDULE VARIANCE - GSE Electrical Charge Stations - $30.7M - Concourse D Hardstand Terminal - $38.4M - Checked Bag Recap Optimization - $445M Off Schedule/Budget $25M or More…
V V